A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should( ).
A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

参考答案:D(仅供参考) 收藏